HC Deb 08 August 1980 vol 990 c486W
Mr. Hudson Davies

asked the Minister of Transport whether any lane closures on the Severn bridge are contemplated during August and September 1980.

Mr. Fowler

As announced in May, engineering work on the bridge to replace a number of hangers will be taking place in August and September. This will require the temporary closing of one lane at off-peak periods during the day and night when weather conditions are suitable.

Opportunity will be taken during these closures to carry out the autumn insection of the carriageway surface, although a minmum number of additional one-lane closures may be necessary. These lane closures will be planned to keep interference with traffic flow to a minimum.