HC Deb 25 May 1979 vol 967 c337W
Mr. Barry Jones

asked the Secretary of State for Wades what is his estimate of the starting date for construction of the Hawarden bypass, its proposed length and estimated cost; and if he will make a statement.

Scheme Gross cost Projected Start
£m date
Firm Programme
A5 Llanfair PG by-pass 4.010 Mid 1981
A5/A5114 Junction Improvement at Nant Turnpike, Llangefni 0.139 Late 1981
A5 Castell Eden Bends, Gwalchmai 0.515 Late 1980
A5 Improvement at Gorad Junction Valley 0.072 1981–82
Under Construction
Britannia Bridge 12.491 April 1980 (completion)
Firm Programme
A5/A55 Bangor By-pass (mainland route to Anglesey) 18.340 Late 1980