HC Deb 20 February 1979 vol 963 c141W
Mr. Roy Hughes

asked the Secretary of State for the Environment what was the original cost and what is the present projected cost of the national ice skating centre in Manchester.

Mr. Denis Howell

I understand that when the Manchester city council first produced its proposals, the cost was expected to be between £7 million and £10 million; and that for the modified project now under discussion with the Sports Council and the National Skating Association, its estimate is £13.8 million.

Mr. Roy Hughes

asked the Secretary of State for the Environment when he expects that the national ice skating centre, Manchester, will be completed; and what was the original expected date.

Mr. Denis Howell

I understand that no completion date has yet been announced for this project, which is still in the planning stages.