§ Mr. Rookerasked the Secretary of State for Social Services what is the current estimate of the completion date of the new accident and trauma unit of the Birmingham General Hospital; and if she will make a statement.
§ Dr. OwenThe Building is planned to be handed over by the contractor at the end of August 1974 and for the three phases to become operational as follows
Accident, Emergency and Physiotherapy Department: mid-September.Theatres, Intensive Therapy Unit and Coronary Care Unit: mid-October.Ward Units: mid-November.