asked the Secretary of State for Social Services what is the value of sums held under the liability defects clause inserted into building contracts in respect of hospitals.

Mr. Alison

The information is not readily available. The Department has recommended Hospital Boards to retain a proportion of the contract sum to cover the defects liability period on the following scale:

  • For contracts up to £100,000–5 per cent.
  • For contracts between £100,000 and £1 million—3 per cent.
  • For contracts exceeding £1 million—2½ per cent.