§ Mr. Woofasked the Minister of Technology when he now expects the Dungeness B nuclear power station to be in operation; what delay that represents by comparison with the original estimate; and what has been the increase in the estimated costs.
Mr. Alan WilliamsAs regards the delay I would refer my hon. Friend to the reply to my hon. Friend the Member for Bassetlaw (Mr. Ashton), on 22nd October. The increase in the C.E.G.B.'s estimate of cost is £12/KW.—[Vol. 788, c. 278.]