Mr. Channon

asked the Minister of Transport how many contracts for building and civil engineering works let by agent authorities of her Department, which have an estimated completion date of May, 1968 or later in the United Kingdom, her department entered into before 3rd May, 1966 with a standard form of contract without a variation clause; and what is the total value of he contracts.

Mr. John Morris

Three, of a total value of £7.3 million, excluding contracts under £100,000, details of which could not be given without a disproportionate expenditure of time and labour.

Mr. Channon

asked the Minister of Transport how many contracts for building and. civil engineering works let by agent authorities of her Department in the United Kingdom, which have an estimated completion date of between May, 1967 and May, 1968, her department entered into before 3rd May, 1966 with a standard form of contract without a variation clause; and what is the total value of the contracts.

Mr. John Morris

Twenty two, of a otal value of £28.5 million, excluding contracts under £100,000, details of which could not be given without a disproportionate expenditure of time and labour.