HC Deb 09 May 1960 vol 623 c1W
1. Mr. C. Hughes

asked the Minister of Health the reasons for the delay in completing the extensions to the Caernarvon and Anglesey Infirmary at Bangor; and if he will make a statement.

Miss Pitt

The contract was due for completion in August, 1959, but additional work was authorised and this, together with bad weather and site and labour difficulties made it necessary to extend the contract period. Completion is now expected by the end of June.