HC Deb 03 March 1954 vol 524 c89W
27. and 28. Mr. Bence

asked the First Lord of the Admiralty (1) the cost to date of the Royal Yacht "Britannia"; and how much this is in excess of the original estimate;

(2) when the Royal Yacht "Britannia" is to be completed.

Mr. J. P. L. Thomas

The amount actually spent on the Royal Yacht to date is approximately £1,900,000. The original estimate of the total cost at prices ruling in November, 1952 was £1,800,000; the present estimate, based on the latest information available, is some £2,100,000. She was accepted into service on 11th January.