HC Deb 10 February 1930 vol 235 c49W
Mr. BUCHANAN

asked the First Commissioner of Works if he is aware that work is not now proceeding at the building of the Exchange in Glasgow; if he can state the reason for this hold-up; and if ho will take steps to see that it is undertaken at once?

Mr. LANSBURY

I understand that work is proceeding normally on the new Employment Exchange in Glasgow; work on the site was stopped for one day only as the contract for the foundations had to be finished before the contractor for the steelwork could start.