HC Deb 14 June 1989 vol 154 c411W
Mr. Cohen

To ask the Secretary of State for Transport if he will indicate his estimates of repairs and maintenance for each of the M11 and M25 for each of the next five years.

Mr. Peter Bottomley

The need for repairs and maintenance of motorways is reviewed each year in the light of condition surveys. Major maintenance work for the M11 and M25 has been planned for 1989–90, as follows:

Location Works Cost £ million
M11
Junctions 12–14 Overlay 1.0
South of Junction 5 (Northbound) Overlay 2.6
South of Junction 5 (Southbound) Overlay 2.9
North of Junction 5 (Northbound) Overlay 1.3
North of Junction 5 (Southbound) Overlay 1.2
Total cost 9.0
M25
Junction 24 Reconstruction 2.9
Junctions 11–13 Reconstruction 0.9
Total cost 3.8