§ Mr. Speedasked the Secretary of State for Transport if he will list his latest estimates of the completion dates of the remaining sections of the M25 motorway.
§ Mr. Kenneth ClarkeThirty six miles of the route are already open. The estimated opening dates of the remaining sections are shown below. These are subject in some cases to satisfactory completion of the statutory procedures:
460W
Section Length (miles) Estimated opening date A111–A10 5.3 20 July 1981 *A10–M11 7.6 1983 *M11–A12 8.0 1983 *A12–A13 9.3 1983 Swanley-Sevenoaks 8.6 1985 Reigate-Wisley 12.1 1984 Wisley-Chertsey 6.1 1983 *Egham-Yeoveney 1.2 1981 *Yeoveney-Airport Spur 1.9 1983 Airport Spur-M4 1.8 1985 M4-Maple Cross 11.0 1985
Section Length (miles) Estimated opening date Micklefield Green-South Mimms 12.0 1986 * Under construction.