HC Deb 28 June 1974 vol 875 c61W
Sir P. Bryan

asked the Secretary of State for the Environment when he now expects the sections of the M62 now under construction to be completed.

Mr. Carmichael

The estimated completion dates are as follows:

Section Estimated completion date
Queens Drive, Liverpool-Tar bock Early 1976
Risley-Worsley August 1974
Lofthouse-Ferrybridge July-August 1974
Ferrybridge-Pollington October 1974 (Part of the route eastwards of Ferrybridge may be opened earlier)
Pollington-Rawcliffe Late 1975
Rawcliffe-Balkholme End 1975
Balkholme-Caves End 1975