HL Deb 05 July 1966 vol 275 cc1054-5WA
THE EARL OF SELKIRK

asked Her Majesty's Government:

What is the extent of the improvements on road A.31 which it is intended to carry out and when they are likely to be completed.

THE MINISTER WITHOUT PORTFOLIL (LORD CHAMPION)

The following schemes for the further improvement.

Scheme Estimated Cost £ Start of Work Estimated Completion Date
Dualling—Hogs Back Stage I 89,000 5.66 2.67
Stage II 95,000 5.66 2.67
Stage III 65,000 5.66 2,67
Extension of Farnham By-pass 480,000 7.66 1.68
South Street flyover Farnham 700,000 4.68 12.69
Dualling—Puttenham Crossroads to Tongham 480,000 5.69 11.70
Dualling—Pauncefoot Hill 84,000 4.66 3.67
Alton By-pass (including by-pass of Chawton) 1,575,000 4.68 3.70
Ashley—Treening Diversion 909,000 10.66 12.67
Dualling—Boundary Lane to Oaks Lane 31,000 4.66 8.66
Poulner Hill 95,000 Spring '67 1968
Poulner Hill to Picket Post 96,000 5.67 3.68
Bratley Arch 32,000 9.66 3.67
Tricketts Cross to Hants. County Boundary 130,000 5.66 5.67
Junction with Hayes Lane 30,000 1966–67 1967–68
Wimborne Minster—Southern Relief Road 196,000 Before 1970 approx. 18 months later