§ Mr. Wallasked the Minister of Transport whether he will provide a list of road schemes in Yorkshire which have been delayed in connection with the proposals for reducing immediate capital commitments; whether he will give an assurance that none of these will be delayed for more than six months; and whether he will give revised starting dates of each.
155W
§ Mr. Tom FraserDetails of schemes costing over £100,000 and the revised target starting dates are given below. A prompt start on the new dates depends on satisfactory progress with land acquisition and other preparatory work.
Revised target starting date M.1 (Aston-Leeds section) (a) Tankersley-Darton June, 1966 (b) Darton-Horbury July, 1966 A.63 Widening through Garforth village April, 1966 A.647 Stanningley By-pass (Stage 1) March, 1966 A.639 Haigh Cottages-Oulton April, 1966 A.642 Horbury By-pass March, 1966