§ 65. Sir A. Hurdasked the Minister of Transport when he expects work will be completed on the north-south relief road through Newbury; and what are the reasons for the delay in constructing the replacement railway bridge which is aggravating the normal traffic congestion in the town.
§ Mr. GalbraithWork on the replacement bridge is behind schedule because 173W of delay in the supply of pre-cast beams for the super-structure. But I expect the scheme to be finished well before the contract expires in September, 1965.