§ 66. Mr. Remnantasked the Minister of Health the amount of the accepted tenders for the additions to Heather-wood Hospital, and the Wokingham 68W Maternity Wing, respectively, and the contract dates for completion.
§ Mr. R. ThompsonI do not think it is wise to disclose the amounts of tenders for hospital building, but the estimated costs of these two projects including fees and equipment are, approximately, £170,000 for Heatherwood Hospital and £110,000 for Wokingham Maternity Unit. The contract dates for the completion of building work are, for Heatherwood, January 1961, and for Wokingham, March 1960.