§ Sir T. Mooreasked the Secretary of State for Scotland if he will issue a list of schemes under the road programme, costing over £100,000 which were started
Scheme Starting date Estimated Completion date Estimated total cost £ TRUNK ROADS 1. A.74—Improvement from Dalmakethar to North of Lockerbie. July, 1958 Autumn, 1960 518,000 2. A.830—Improvement from Glenfinnan to Lochailort November, 1958 End, 1961 420,000 CLASSIFIED ROADS 3. A.884—Reconstruction of 3¼ miles of Achleck-Lochaline Pier Road. July, 1958 Spring, 1960 155,000 4. Forth Road Bridge—Construction of bridge and approach roads. September, 1958 1963–64 16,000,000 In addition, the following scheme has been started since the period covered by my reply of 17th April last to my hon. and gallant Friend:—
30W
TRUNK ROAD A.80—Improvement from Luggie Water to west of Cumbernauld. April, 1958 Spring, 1960 434,000 respectively to posters, including bulletin boards but not trade signs, public information panels, and to trade signs on the premises of the occupiers concerned; and how many of each separate category were rejected or allowed.
§ Mr. MaclayThe total number of appeals decided during 1958 was 36, in addition to 14 that were withdrawn. The appeals decided were dealt with at hearings to which the public could have had access, with one exception dealt with by correspondence at the request of the appellants. None related to public information panels. Details are as follows:
in the six months ended 31st December, 1958, with estimated completion date and total cost of each.
§ Mr. MaclayThe following is a list of the schemes referred to: