HC Deb 22 March 1995 vol 257 c341
10. Sir David Steel

To ask the Secretary of State for Scotland how much has been spent to date, including land acquisition costs, on (a) the A7 Falla Hill to Heriot improvement, (b) the A7 Bow Straight widen and regrade and (c) the A7 Whin improvement. [13635]

Lord James Douglas-Hamilton

The total expenditure, including land acquisition costs, on the A7 Falla Hill to Heriot improvement, the widening and regrading of the A7 Bow Straight and the A7 Whin improvement is £49,811, £5,405 and £35,523 respectively.

Sir David Steel

It would be helpful if the Minister could inform the House when the decision is likely to be taken about detrunking roads such as the A7. Does he accept that it would be intolerable if the cost of the improvements that he has outlined were to fall on the new Borders council without a guarantee that extra funds will be provided for that purpose?

Lord James Douglas-Hamilton

Decisions will be made shortly about the trunking or detrunking of various roads in Scotland. The three schemes that I have mentioned are old schemes which will provide overtaking opportunities. Each of the three jobs will cost £1.5 million, making a total of £4.5 million. Primarily for environmental reasons, we believe that it would be more beneficial at present to spend that sum on the A68. The sum, approaching £100,000, which has been spent so far is not necessarily lost or wasted as the new authority can take it forward if the road is detrunked.