Heading: |
Energy Supply and National Grid: Costs |
Question ID: |
1825166 |
UIN: |
HL9714 |
House: |
Lords |
Date tabled: |
2025-07-21 |
Asking Member ID: |
4937 |
Asking Member display name: |
Lord Strathcarron
|
Asking Member handle: |
|
Asking Member Twitter reference: |
Lord Strathcarron
|
Member interest: |
false |
Question text: |
To ask His Majesty's Government why the cost of upgrading the electricity grid is estimated at £60 billion in the report Clean Power 2030, published on 5 November 2024 by the National Energy System Operator, and at £80 billion in the Ofgem press release o |
Is named day: |
false |
Date of holding answer: |
|
Date answered: |
2025-07-31 |
Date answer corrected: |
|
Is holding answer: |
false |
Is correcting answer: |
false |
Answering Member ID: |
1603 |
Answering Member display name: |
Lord Wilson of Sedgefield
|
Answering Member handle: |
|
Answering Member Twitter reference: |
Lord Wilson of Sedgefield
|
Correcting Member ID: |
|
Correcting Member display name: |
|
Correcting Member handle: |
|
Correcting Member Twitter reference: |
|
Answer text: |
The £80bn cost estimate in Ofgem’s Draft Determinations for RIIO ET3, which covers 2026/27 to 2030/31, is not exclusively spending required to deliver the transmission network needed to deliver 2030 Clean Power, but also takes into account wider operation... |
Original answer text: |
|
Comparable answer text: |
|
Answering body ID: |
215 |
Answering body name: |
Department for Energy Security and Net Zero |
Tweeted: |
true |