To ask His Majesty's Government what assessment they have made of the cost of HS2 to date, and how much it will cost to complete the project in current prices. |
Is named day: |
false |
Date of holding answer: |
|
Date answered: |
2025-06-27 |
Date answer corrected: |
|
Is holding answer: |
false |
Is correcting answer: |
false |
Answering Member ID: |
4972 |
Answering Member display name: |
Lord Hendy of Richmond Hill
|
Answering Member handle: |
|
Answering Member Twitter reference: |
Lord Hendy of Richmond Hill
|
Correcting Member ID: |
|
Correcting Member display name: |
|
Correcting Member handle: |
|
Correcting Member Twitter reference: |
|
Answer text: |
Mark Wild, the new CEO of HS2 Ltd, is leading a comprehensive reset of the programme to deliver the remaining works at the lowest reasonable cost. As part of this work, he will advise the Department on a revised cost estimate for HS2. As Mark Wild set ou... |