Heading: |
Boeing E-7: Cost Effectiveness |
Question ID: |
1813009 |
UIN: |
59991 |
House: |
Commons |
Date tabled: |
2025-06-16 |
Asking Member ID: |
1444 |
Asking Member display name: |
Mr Mark Francois
|
Asking Member handle: |
|
Asking Member Twitter reference: |
Mr Mark Francois
|
Member interest: |
false |
Question text: |
To ask the Secretary of State for Defence, what steps his Department has taken to ensure the (a) financial accountability and (b) value for money of the E-7 Wedgetail programme; and what assessment he has made of the potential merits of launching an indep |
Is named day: |
true |
Date of holding answer: |
|
Date answered: |
2025-06-26 |
Date answer corrected: |
|
Is holding answer: |
false |
Is correcting answer: |
false |
Answering Member ID: |
483 |
Answering Member display name: |
Maria Eagle
|
Answering Member handle: |
meaglemp
|
Answering Member Twitter reference: |
@meaglemp
|
Correcting Member ID: |
|
Correcting Member display name: |
|
Correcting Member handle: |
|
Correcting Member Twitter reference: |
|
Answer text: |
Identified as part of the Government Major Project Portfolio (GMPP), the Wedgetail programme is subject to regular reviews by the National Infrastructure and Service Transformation Authority who undertake regular assessment of the E-7 programme and report... |