A question on #SizewellCPowerStation #Finance tabled by Lord West of Spithead on 19-05-2025 has been answered by Baroness Curran.

Heading: Sizewell C Power Station: Finance
Question ID: 1803975
UIN: HL7621
House: Lords
Date tabled: 2025-05-19
Asking Member ID: 3834
Asking Member display name: Lord West of Spithead
Asking Member handle:
Asking Member Twitter reference: Lord West of Spithead
Member interest: false
Question text: To ask His Majesty's Government when the final investment decision for the Sizewell C plant will be made, and when the results of the small modular reactor competition will be announced.
Is named day: false
Date of holding answer:
Date answered: 2025-06-03
Date answer corrected:
Is holding answer: false
Is correcting answer: false
Answering Member ID: 3982
Answering Member display name: Baroness Curran
Answering Member handle:
Answering Member Twitter reference: Baroness Curran
Correcting Member ID:
Correcting Member display name:
Correcting Member handle:
Correcting Member Twitter reference:
Answer text: As confirmed at the Autum Budget, both the equity and debt raise processes are in their final stages. A final decision on whether to proceed with the project will be made at the Spending Review. Great British Nuclear is driving forward its small modular r...
Original answer text:
Comparable answer text:
Answering body ID: 215
Answering body name: Department for Energy Security and Net Zero
Tweeted: true