A question on #FloodControl #Licensing tabled by Jonathan Davies on 16-05-2025 has been answered by Emma Hardy.

Heading: Flood Control: Licensing
Question ID: 1803740
UIN: 52957
House: Commons
Date tabled: 2025-05-16
Asking Member ID: 5256
Asking Member display name: Jonathan Davies
Asking Member handle: Jonathan4MD
Asking Member Twitter reference: @Jonathan4MD
Member interest: false
Question text: To ask the Secretary of State for Environment, Food and Rural Affairs, what the average length of time was between the Environment Agency receiving a flood risk activity permit application and starting the determination process for the approval of said pe
Is named day: false
Date of holding answer:
Date answered: 2025-05-22
Date answer corrected:
Is holding answer: false
Is correcting answer: false
Answering Member ID: 4645
Answering Member display name: Emma Hardy
Answering Member handle:
Answering Member Twitter reference: Emma Hardy
Correcting Member ID:
Correcting Member display name:
Correcting Member handle:
Correcting Member Twitter reference:
Answer text: Flood risk activity permit applications are currently being allocated for assessment a maximum of 14 weeks from receipt. For time critical applications that pose a significant risk to people or the environment, or where required for national infrastructur...