A question on #DataCentres #Energy tabled by Lord Taylor of Warwick on 31-03-2025 has been answered by Lord Hunt of Kings Heath.

Heading: Data Centres: Energy
Question ID: 1790904
UIN: HL6380
House: Lords
Date tabled: 2025-03-31
Asking Member ID: 1796
Asking Member display name: Lord Taylor of Warwick
Asking Member handle: Lord_ofWarwick
Asking Member Twitter reference: @Lord_ofWarwick
Member interest: false
Question text: To ask His Majesty's Government what steps they are taking to ensure connections to the electricity grid are sufficient to attract investment in artificial intelligence data centre infrastructure.
Is named day: false
Date of holding answer:
Date answered: 2025-04-14
Date answer corrected:
Is holding answer: false
Is correcting answer: false
Answering Member ID: 2024
Answering Member display name: Lord Hunt of Kings Heath
Answering Member handle: lordphilofbrum
Answering Member Twitter reference: @lordphilofbrum
Correcting Member ID:
Correcting Member display name:
Correcting Member handle:
Correcting Member Twitter reference:
Answer text: The Government is working with Ofgem and NESO to deliver fundamental reform to the grid connections process. Subject to Ofgem’s final decision this could release over 400GW of capacity from the connection queue, which will accelerate connections for AI da...