Question text: |
To ask His Majesty's Government, following the publication on 19 February of Current PFI and PF2 projects as at 31 March 2024, why the A69 Carlisle to Newcastle project (project ID 245) incurred payments in 2023–24 of £14 million on a capital value of £9 |
Is named day: |
false |
Date of holding answer: |
|
Date answered: |
2025-04-10 |
Date answer corrected: |
|
Is holding answer: |
false |
Is correcting answer: |
false |
Answering Member ID: |
4972 |
Answering Member display name: |
Lord Hendy of Richmond Hill
|
Answering Member handle: |
|
Answering Member Twitter reference: |
Lord Hendy of Richmond Hill
|
Correcting Member ID: |
|
Correcting Member display name: |
|
Correcting Member handle: |
|
Correcting Member Twitter reference: |
|
Answer text: |
The A69 Carlise to Newcastle Project is a 30-year PFI project expiring in March 2026. At financial close in 1996, the project comprised of the design and build of Haltwhistle Bypass, a 2-mile section of the A69, and the maintenance and renewal of the 52-m... |