Heading: |
New Palace Yard: Repairs and Maintenance |
Question ID: |
1749903 |
UIN: |
20032 |
House: |
Commons |
Date tabled: |
2024-12-13 |
Asking Member ID: |
4778 |
Asking Member display name: |
Greg Smith
|
Asking Member handle: |
gregsmith_uk
|
Asking Member Twitter reference: |
@gregsmith_uk
|
Member interest: |
false |
Question text: |
To ask the hon. Member for Blaenau Gwent and Rhymney, representing the House of Commons Commission, whether the work for vehicle entry and exit in New Palace Yard is on (a) time and (b) budget. |
Is named day: |
false |
Date of holding answer: |
|
Date answered: |
2025-01-07 |
Date answer corrected: |
|
Is holding answer: |
false |
Is correcting answer: |
false |
Answering Member ID: |
3928 |
Answering Member display name: |
Nick Smith
|
Answering Member handle: |
BlaenauGwentMP
|
Answering Member Twitter reference: |
@BlaenauGwentMP
|
Correcting Member ID: |
|
Correcting Member display name: |
|
Correcting Member handle: |
|
Correcting Member Twitter reference: |
|
Answer text: |
The most recently approved Business Case for the works in New Palace Yard anticipated a completion date of between October 2024 and March 2026. This range takes into account identified risks that may occur over the life span of the project, for example ma... |
Original answer text: |
|
Comparable answer text: |
|
Answering body ID: |
18 |
Answering body name: |
House of Commons Commission |
Tweeted: |
true |