A question on #PalaceOfWestminster #RepairsAndMaintenance tabled by Lord Colgrain on 18-12-2024 has been answered by Lord Gardiner of Kimble.

Heading: Palace of Westminster: Repairs and Maintenance
Question ID: 1751366
UIN: HL3594
House: Lords
Date tabled: 2024-12-18
Asking Member ID: 4596
Asking Member display name: Lord Colgrain
Asking Member handle:
Asking Member Twitter reference: Lord Colgrain
Member interest: false
Question text: To ask the Senior Deputy Speaker what has been the cost of the work on the Restoration and Renewal programme since 2012 in respect of (1) the salaries, recruitment fees, and redundancy payments for non-parliamentary staff, such as those working for the Sp
Is named day: false
Date of holding answer:
Date answered: 2025-01-06
Date answer corrected:
Is holding answer: false
Is correcting answer: false
Answering Member ID: 4161
Answering Member display name: Lord Gardiner of Kimble
Answering Member handle:
Answering Member Twitter reference: Lord Gardiner of Kimble
Correcting Member ID:
Correcting Member display name:
Correcting Member handle:
Correcting Member Twitter reference:
Answer text: The Parliamentary Works Sponsor Body and Restoration and Renewal (R&R) Delivery Authority were established in April and May 2020 respectively. The Sponsor Body was abolished on 1 January 2023 and its functions transferred to the R&R Client Team in...
Original answer text:
Comparable answer text:
Answering body ID: 213
Answering body name: Restoration and Renewal Client Board
Tweeted: true