Heading: |
Palace of Westminster: Repairs and Maintenance |
Question ID: |
1751366 |
UIN: |
HL3594 |
House: |
Lords |
Date tabled: |
2024-12-18 |
Asking Member ID: |
4596 |
Asking Member display name: |
Lord Colgrain
|
Asking Member handle: |
|
Asking Member Twitter reference: |
Lord Colgrain
|
Member interest: |
false |
Question text: |
To ask the Senior Deputy Speaker what has been the cost of the work on the Restoration and Renewal programme since 2012 in respect of (1) the salaries, recruitment fees, and redundancy payments for non-parliamentary staff, such as those working for the Sp |
Is named day: |
false |
Date of holding answer: |
|
Date answered: |
2025-01-06 |
Date answer corrected: |
|
Is holding answer: |
false |
Is correcting answer: |
false |
Answering Member ID: |
4161 |
Answering Member display name: |
Lord Gardiner of Kimble
|
Answering Member handle: |
|
Answering Member Twitter reference: |
Lord Gardiner of Kimble
|
Correcting Member ID: |
|
Correcting Member display name: |
|
Correcting Member handle: |
|
Correcting Member Twitter reference: |
|
Answer text: |
The Parliamentary Works Sponsor Body and Restoration and Renewal (R&R) Delivery Authority were established in April and May 2020 respectively. The Sponsor Body was abolished on 1 January 2023 and its functions transferred to the R&R Client Team in... |
Original answer text: |
|
Comparable answer text: |
|
Answering body ID: |
213 |
Answering body name: |
Restoration and Renewal Client Board |
Tweeted: |
true |