Question text: |
To ask the Secretary of State for Transport, if she will make an estimate of the potential impact of the time taken to determine the application for the A12 Junction 19 to Junction 25 widening scheme on (a) the economy, (b) road safety and (c) the cost of |
Is named day: |
false |
Date of holding answer: |
|
Date answered: |
2024-12-06 |
Date answer corrected: |
|
Is holding answer: |
false |
Is correcting answer: |
false |
Answering Member ID: |
4029 |
Answering Member display name: |
Lilian Greenwood
|
Answering Member handle: |
LilianGreenwood
|
Answering Member Twitter reference: |
@LilianGreenwood
|
Correcting Member ID: |
|
Correcting Member display name: |
|
Correcting Member handle: |
|
Correcting Member Twitter reference: |
|
Answer text: |
The Development Consent Order (DCO) application for the A12 Chelmsford to A120 widening scheme, was granted on 12 January 2024. I can confirm that the DCO was determined within the statutory timeframes. |