A question on #NationalGrid tabled by James Cartlidge on 02-12-2024 has been answered by Michael Shanks.

Heading: National Grid
Question ID: 1746157
UIN: 17189
House: Commons
Date tabled: 2024-12-02
Asking Member ID: 4519
Asking Member display name: James Cartlidge
Asking Member handle: jcartlidgemp
Asking Member Twitter reference: @jcartlidgemp
Member interest: false
Question text: To ask the Secretary of State for Energy Security and Net Zero, pursuant to the Answer of 26 November 2024 to Question 16211 on National Grid: Costs of the Western and Eastern Links, whether (a) he and (b) Ofgem is able to provide the estimate requested.
Is named day: true
Date of holding answer:
Date answered: 2024-12-05
Date answer corrected:
Is holding answer: false
Is correcting answer: false
Answering Member ID: 4998
Answering Member display name: Michael Shanks
Answering Member handle: mgshanks
Answering Member Twitter reference: @mgshanks
Correcting Member ID:
Correcting Member display name:
Correcting Member handle:
Correcting Member Twitter reference:
Answer text: The analysis of an onshore reinforcement (i.e. overhead pylons) for Western Green Link was conducted 16 years ago and cost estimates for alternative options are not available.As the option of an onshore reinforcement for Eastern Green Link 1&2 did not...