A question on #CabinetOffice #ICT tabled by Mr Richard Holden on 27-11-2024 has been answered by Ms Abena Oppong-Asare.

Heading: Cabinet Office: ICT
Question ID: 1745048
UIN: 16511
House: Commons
Date tabled: 2024-11-27
Asking Member ID: 4813
Asking Member display name: Mr Richard Holden
Asking Member handle: RicHolden
Asking Member Twitter reference: @RicHolden
Member interest: false
Question text: To ask the Minister for the Cabinet Office, what changes have been made to the planned delivery date of the Rosa Renewal Project since inception.
Is named day: false
Date of holding answer:
Date answered: 2024-12-05
Date answer corrected:
Is holding answer: false
Is correcting answer: false
Answering Member ID: 4820
Answering Member display name: Ms Abena Oppong-Asare
Answering Member handle: abenaopp
Answering Member Twitter reference: @abenaopp
Correcting Member ID:
Correcting Member display name:
Correcting Member handle:
Correcting Member Twitter reference:
Answer text: The Rosa Renewal Project remains on track to complete by March 2025. It is an agile project planned to ensure the resilience of HMG’s existing shared service capability for working on very sensitive information, and managed under the Government Major Proj...
Original answer text:
Comparable answer text:
Answering body ID: 53
Answering body name: Cabinet Office
Tweeted: true