HC Deb 23 October 2003 vol 411 c16WS
The Minister of State, Ministry of Defence (Mr. Adam Ingram)

Key Targets have been set for the Chief Executive of the Warship Support Agency for financial year 2003–04. The targets build on progress already made and are as follows:

Key Target 1: Quantity

To meet the 100 per cent. available vessel days target.

Key Target 2: Timeliness

To meet the <6.5 per cent. upkeep period timeliness target.

Key Target 3: Timeliness

To achieve the 95 per cent. target for timely completion of the high priority upgrade programme.

Key Target 4: Quality

To achieve the Operational Support Services target of providing the appropriate standard of single living accommodation to 35 per cent. of naval personnel.

Key Target 5: Quality

To achieve the Operational Support Services target of meeting the Customers Needs ISO Quality Control Comment Form targets, as follows:

Group 1–0 failures Group 2–0 failures

Group 3 <5 per cent. failure

Key Target 6: Quantity

To generate the capacity to support the Naval Force Generation Plan target with Green assessments against all elements.

Key Target 7: Cost/Efficiency

To make the necessary Agency contribution to the Defence Logistics Organisation Strategic Goal of reducing Output Costs by 20 per cent. by 2005 whilst ensuring that we continue to deliver and, where appropriate, improve the quality of our outputs.