HC Deb 14 October 2003 vol 411 cc5-6WS
The Parliamentary Under-Secretary of State for Transport (Mr. Tony McNulty)

Regulations under section 74 of the New Road and Street Works Act 1991 came into force in April 2001. These allow highway authorities to charge utility companies for works in the street which overrun an agreed deadline.

Following the implementation of these powers my Department appointed consultants, Halcrow, to monitor their effectiveness in reducing disruption on the highway. Copies of Halcrow's first annual report were placed in the libraries of both Houses last autumn.

Halcrow have now produced their second annual report on these powers: Assessing the Extent of Street Works and Monitoring the Effectiveness of Section 74 in Reducing Disruption. The report consists of two volumes; Volume 1 is the main report and Volume 2 contains accompanying tables and charts. Copies of each have been placed in the Libraries of both Houses.