HC Deb 09 September 2004 vol 424 c1337W
Mr. Wiggin

To ask the Secretary of State for Transport how many transport-related projects on the(a) railways and (b) roads are running (i) on schedule and (ii) behind schedule. [186801]

Mr. McNulty

There are nine major programmes of enhancement work currently contracted on the railways, each comprising many individual projects. Of these, eight are on schedule in line with the agreed works programme, and one is behind schedule.

There are 16 major new road schemes currently contracted on the Strategic Road Network. 13 are on schedule to complete in line with the programme planned at Works Commitment stage, three schemes are behind schedule, one by several months and two by no more than six weeks.

There are 27 major road and road maintenance schemes which are currently fully accepted within the local transport programme. Of these, 13 are on schedule to complete in line with the timetable planned at full acceptance stage. 14 schemes are behind schedule, some only marginally.