HC Deb 10 June 2004 vol 422 c600W
Mr. Gerald Howarth

To ask the Secretary of State for Defence what percentage of the total projected budget of the Future Joint Combat Aircraft was spent prior to main gate approval. [176355]

Mr. Ingram

£144 million was spent on the pre Main Gate Assessment phase of the Joint Combat Aircraft programme. This equates to 6 per cent. of the approved procurement cost to date. This figure excludes expenditure by the United States on the Joint Strike Fighter.