HL Deb 10 March 2003 vol 645 cc152-4WA
Lord Lofthouse of Pontefract

asked Her Majesty's Government:

What action they intend to take to encourage a reversal of the decline in load factors at coal-fired generation plant fitted with flue gas desulphurisation (FGD) equipment and the increase in coal burnt at plant without FGD; and [HL1786]

What plans they have to impose stricter sulphur dioxide emission limits on coal-fired generators that do not have abatement plant fitted. [HL1788]

Lord Whitty

No reliable estimate can yet be made and other factors will also influence this market. The implementation option under the revised Large Combustion Plants Directive (2001/80/EC) for plants licensed before 1987 has not yet been decided. From 2008, those plants must either comply with emission limit values or operate within a national emission plan as established by the directive. Under both, operators can opt to adopt less stringent emission limits subject to committing to closure once they have operated for a maximum of 20,000 hours between 2009 and 2015. Once the implementation decision is taken, all operators, including those with coal-fired generating capacity, must choose whether to close or comply with the measures required by the directive. Those choices have yet to be taken.

Lord Lofthouse of Pontefract

asked Her Majesty's Government:

How much coal-fired generation capacity they expect to be taken out of the market as a result of the implementation of the Larger Combustion Plant Directive. [HL1787]

Lord Whitty

No reliable estimate can yet be made and other factors will also influence this market. The implementation option under the revised Large Combustion Plants Directive (2001/80/EC) for plants licensed before 1987 has not yet been decided. From 2008, these plants must either comply with emission limit values or operate within a national emission plan as established by the directive. Under both, operators can opt to adopt less stringent emission limits subject to committing to closure once they have operated for a maximum of 20,000 hours between 2008 and 2015. Once the implementation decision is taken, all operators, including those with coal-fired generating capacity, must choose whether to close or comply with the measures required by the directive. Those choices have yet to be taken.

Lord Campbell of Croy

asked Her Majesty's Government:

What action is being taken to reduce the amount of sulphur dioxide and other polluting substances being released into the atmosphere from the generation of electricity in coal-fired power stations. [HL1795]

Lord Whitty

Coal-fired power stations are currently regulated by the integrated pollution control (IPC) regime. IPC was established by the Environmental Protection Act 1990 and regulates industrial pollution through a system of authorisation. IPC is being superseded by the integrated pollution prevention and control (IPPC) regime, established by an EC directive of the same name. Installations that came into operation before 31 October 1999 will be regulated by IPPC from 2006. New installations or those undergoing substantial change will be required to apply for an IPPC permit with immediate effect.

IPC requires operators to demonstrate that they will use the best available techniques not entailing excessive cost (BATNEEC) for their activities. BATNEEC has to be applied to prevent or minimise the release of prescribed substances and to render harmless any such substances which are released to air, water and land. If releases are made to more than one environmental medium, the best practicable environmental option is applied. The regulator assesses BATNEEC on a site-by-site basis and keeps authorisations under review. Depending on the characteristics of the plant, BATNEEC may include the use of flue gas desulphurisation.

In an IPPC permit application, operators are required to demonstrate that they will use the best available techniques (BAT) to control pollution from their activities. BAT aims to prevent, and where that is not practicable, to reduce to acceptable levels, emissions from the activities. BAT also aims to balance the cost to the operator against the benefits to the environment, and is assessed by the regulator on a site-by-site basis, taking into account European guidance on what constitutes BAT for that sector.

The Government's policies for reducing air pollution were published in January 2000 in Air Quality Strategy for England, Scotland, Wales and Northern Ireland. The strategy contains standards for eight main pollutants of concern, including sulphur dioxide, below which significant risks to public health are likely to occur. The air quality strategy sets target dates for the standards to be achieved. The latest data suggests the 2004 and 2005 targets will be met across most of the UK. The 2005 target for sulphur dioxide is the most stringent.

The UK is a party to the Second Sulphur Protocol under the UN/ECE's Convention on Long-Range Transboundary Air Pollution, whereby SO, emissions must be reduced by 50 per cent by 2000, 70 per cent by 2005 and 80 per cent by 2010 (all from a 1980 baseline). The UK is well on track to meet these targets, and by the end of 2000 had achieved a 76 per cent reduction from 1980 baseline levels.

Within the EU, the National Emission Ceilings Directive sets emission ceilings for certain pollutants to be achieved by 2010, and the UK reduced its SO2 ceiling to 585ktonnes. The directive is part of the Eli's Acidification Strategy, where one of the overall aims is to reduce by 50 per cent the areas of European ecosystems receiving excessive levels of acid pollution (exceeding their critical loads).

Emission limit values for pollutants likely to be emitted in significant quantities must be set in an IPC authorisation or IPPC permit and would reflect the requirements of these instruments.