HL Deb 02 June 2003 vol 648 c111WA
Lord Laird

asked Her Majesty's Government:

What capital projects and track maintenance have taken place on the Northern Ireland Railway Companies line between Ballymena and Londonderry since 1 January 1997; and what new capital and maintenance work is proposed for this line in the next two years. [HL2634]

The Lord Privy Seal (Lord Williams of Mostyn):

Translink has advised that since 1 January 1997 the following capital projects have been carried out on the line between Ballymena and Londonderry:

at Ballymena, Coleraine and Castlerock stations there has been excavation and replacement of spent ballast, removal and renewal of bull-head rail on timber sleepers with new concrete sleepers and rail used as necessary;

continuous welded rail has been installed on the line adjacent to City of Derry airport and half a mile west of Downhill;

work has been carried out on rail bridges and footbridges at various locations including Ballymoney, Cullybackey, Coleraine, Bellarena, Londonderry and Greysteel;

approximately 70 metres of sea defences at Enagh, south west of Lisnahally, have been repaired.

Consultants Fees Project Appointed
PWC recruitment consultancy £66,300 Executive resourcing assignment in connection with the recruitment of the chief executive. Appointed under the terms of the human resources recruitment contract for all cross-Border bodies.
PWC Consultancy (IT) £100,000 IT Consultancy to provide expert advice in preparation for major financial and Human Resources contracts etc. Contract awarded as an extension of an existing contract for similar work already commissioned by the Department of Arts, Heritage, Gaeltacht and the Islands (including the Waterways Division of that department).
OMI Equality Consultation £6,700 Equality. Selected off an approved list of consultants capable of providing equality training.