HL Deb 09 July 2003 vol 651 cc42-3WA
Lord Hogg of Cumbernauld

asked Her Majesty's Government:

What key targets have been set for the Defence Procurement Agency for financial year 2003–04. [HL3915]

Lord Bach

Five key targets have been set for the chief executive of the Defence Procurement Agency for the financial year 2003–04.

The first three key targets apply to projects covered by the major projects report which have passed their main gate approval. Key targets two and three are consistent with the goals set in the department's public service agreement (PSA). The fourth key target relates to improvements in DPA customer satisfaction and the fifth to the costs of running the agency. The key targets are:

Key target 1Key requirements compliance

Predicted achievement of customers' core requirements1 for projects: 98 per cent

Key target 2Average in-year in service date slippage

Average in-year slippage of in service dates2 compared with approval not to exceed 0.5 months

Key target 3Average in-year cost growth

Average in-year cost variation3 not to exceed 0 per cent

Key target 4Customer survey satisfaction rating Customer satisfaction rating of 74 per cent

Key target 5: Agency running costs

No excess against DPA resource control totals.

1 Around 10 core requirements per projects are agreed between the DPA and MoD headquarters, defining the essential characteristics of the equipment/capability

2 Variation between in service date (ISD) approved at "Main Gate" (the major investment decision point) and currently predicted ISD

3 Variation between costs approved at Main Gate and current predicted estimate