HC Deb 27 November 2002 vol 395 c336W
Mr. Hancock

To ask the Secretary of State for Defence how much has been spent on the PFI contracts for(a) the Germany white fleet, (b) MHE vehicles and (c) the RAF white fleet; when the contracts were completed; and if he will make a statement. [82258]

Mr. Ingram

Spend and completion dates for the specified PFI contracts are as follows:

  • Germany white fleet—total spend to date £87.8 million; the contract is due for completion in March 2004.
  • MHE Vehicles—total spend was £16.4 minion; the contract was completed in August 2002.
  • RAF white fleet—total spend to date £65 million; the contract has been
  • extended to run until negotiations for its re-let are concluded.

Mr. Hancock

To ask the Secretary of State for Defence how much has been spent on the PFI contracts for(a) the hazardous stores information system, (b) the Yeovilton family quarters, (c) DFTS, (d) electronic messaging service (Armymail), (e) the Hawk simulator, (f) Tidworth water and sewerage, (g) DHFS (Helicopter Flying School) and (h) TAFMIS (IT); whether the contracts are on schedule; and if he will make a statement. [82266]

Mr. Ingram

I will write to the hon. Member and a copy of my letter will be placed in the Library of the House.