HC Deb 20 March 2002 vol 382 cc357-8W
Mr. Key

To ask the Secretary of State for Transport, Local Government and the Regions what the timetable is for the laying of orders, planning procedures and construction in respect of the A303 (T) relating to (a) Winterbourne Stoke Bypass, (b) the Amesbury to Berwick Down improvement scheme, (c) the Countess Roundabout flyover and Stonehenge Visitors Centre access and (d) the Folly Bottom interchange. [44429]

Mr. Jamieson

The Highways Agency is planning to publish draft orders for the A303 Stonehenge Improvement in December 2002. This scheme, formerly known as the Amesbury to Berwick Down Improvement, incorporates a bypass of Winterbourne Stoke and a flyover at Countess Roundabout. Subject to the making of statutory orders, it is intended that construction will start in the spring of 2005.

The agency proposes to publish the made orders for the Folly Bottom interchange in April 2002. Preliminary works are expected to start in June 2002 and the main works in September 2002.

The Stonehenge Visitors Centre is the responsibility of English Heritage who will in due course be discussing access arrangements with the Highways Agency.

Forward to