HC Deb 13 March 2002 vol 381 c1162W
Mr. Gerald Howarth

To ask the Secretary of State for Defence what is the(a) estimated total project cost of, (b) total expenditure to date and (c) planned expenditure in each of the next three years on the multi-role armoured vehicle project. [42258]

Dr. Moonie

The total estimated procurement cost of the multi-role armoured vehicle is expected to exceed £1 billion. Expenditure to date amounts to some £20 million. I am withholding the information requested on planned expenditure for each of the next three years in accordance with Exemption 2 of the Code of Practice on Access to Government Information.