HC Deb 01 March 2002 vol 380 c1583W
Mr. Andrew Turner

To ask the Secretary of State for Trade and Industry for what reason she decided not to hold a public inquiry into the proposed CEFU Croes wind power station in Cardiganshire; and how many applications of similar size have been put before her. [38386]

Mr. Wilson

As with any application under section 36 of the Electricity Act 1989, Ministers have to weigh up all aspects of an application consider all representations—both for and against—and come to a conclusion. In the case of the Cefn Croes application it was concluded that there was sufficient information to approve the application in principle without sending it to public inquiry.

There has been one other application for a 60 megawatt windfarm at Humble Hill, Kielder, Northumberland. It was decided on 29 March 2001 that consent under section 36 of the Electricity Act 1989 could not be given. Copies of the Press Notice and decision letter were placed in the Libraries of the House.

Forward to