HC Deb 22 July 2002 vol 389 cc739-40W
Mrs. May

To ask the Secretary of State for Transport if he will list the major local road improvements, as given in para 6.61, page 65, of the 10-year plan(a) started and (b) completed since July 2000. [71325]

Mr. Jamieson

[holding answer 19 July 2002]: The latest information that we have available from the local authorities shows:

Work on the following major local road schemes has been started and completed since July 2000:

  • Burntwood Bypass Phases I and 2 (Staffordshire)
  • A143 Broome/Ellingham Bypass (Norfolk)
  • A511 Ashby Bypass Stage 2 (Leicestershire).

Work on the following major local road schemes has been completed since July 2000:

  • A174 Skelton and Brotton Bypass (Redcar and Cleveland)
  • Avon Ring Road II: B4465 Shortwood—A420 Warmley (South Gloucestershire)
  • South Thames-side Development Route 4 (Kent)
  • Dearne Towns Link Road (Barnsley)
  • A22 Dualling Nightingale Farm (East Sussex)
  • West Central Route (Newcastle upon Tyne).

Work on the following major local road schemes has been started since July 2000:

  • Bridgwater Northern Distributor Road (Somerset)
  • Dawdon to Seaham Town Centre Link Road (Durham)
  • AI31 Great Leighs Bypass (Essex)
  • A689 Sedgefield to Wynyard Improvement (Durham)
  • A617 Mansfield Ashfield Regeneration Route (Nottinghamshire)
  • Wyre Piddle Bypass (Worcestershire)
  • A53 Hodnet Bypass (Shropshire)
  • A6002/A6007 Coventry Lane Improvement (Nottinghamshire)
  • A6042 Manchester/Salford Inner Relief Road (Manchester/Salford)
  • South Stockton Link (Stockton-on-Tees)
  • Coalfields Link Road Phases 2 and 3 (Barnsley)
  • A6023 Denaby Main Diversion (Doncaster).

Forward to