HC Deb 27 February 2002 vol 380 c1373W
Andrew Mackinlay

To ask the Secretary of State for Transport, Local Government and the Regions if he will make it his policy not to widen the M25 between junctions 12 and 15 within the vicinity of terminal 5. [36853]

Mr. Jamieson

The decision to widen the M25 between Junctions 12 and 15 was made as part of the Roads Review announced in July 1998. This section of road was already severely congested and widening within the existing motorway boundary was considered to be and remains the most appropriate solution. The more recent decision to approve the construction of Terminal 5 at Heathrow Airport will necessitate the construction of a new access road (T5 Spur Road) from T5 to the M25 between Junctions 14 and 15. Both sets of improvements can now be designed and constructed at the same time to limit the delays during construction.