HC Deb 12 February 2002 vol 380 c146W
50. Mr. Pickthall

To ask the hon. Member for Roxburgh and Berwickshire, representing the House of Commons Commission, if he will make a statement on the number of repairs required to the fabric and installations of Portcullis House since it was opened; and what is the estimated total cost. [32388]

Mr. Kirkwood

Contractors are responsible for repairing any faults in their work identified in the 12 months following the hand-over of Portcullis House in August 2000. During the first 12 months some 3,200 defects were identified, ranging from a missing screw to a cracked pane of glass. This is well within the expected norm for a new building of this size and complexity—the vast majority of defects were minor and have not affected the users of the building. The costs of these repairs do not fall to the House of Commons; they are borne by the contractors.

The repairs for which the House has been responsible have mostly been minor and have been carried out as part of the day to day maintenance of the building.