HC Deb 01 February 2002 vol 379 cc596-7W
Mr. Jenkin

To ask the Secretary of State for Defence (1) what extra expenditure has been incurred by his Department as a result of the failure of the advanced short-range air-to-air missile to achieve its original in-service date; and if he intends to claim back the extra expenditure from the manufacturer; [31099]

(2) what the new in-service date for the advanced short-range air-to-air missile is; and if he will make a statement. [31098]

Dr. Moonie

[holding answer 29 January 2002]The Advanced Short Range Air-to-Air Missile (ASRAAM) entered service in January 2002. As a result of a delay in the In Service Date, the Ministry of Defence has incurred additional costs of approximately £7 million. These include extra intramural expenditure and costs arising from the need to maintain Sidewinder missiles in service. During the period in question we have also been without the additional capability provided by the ASRAAM missile. Liquidated damages associated with the late delivery of the missiles are being claimed from the manufacturer. Overall, the total procurement cost of ASRAAM remains less than the original approved cost.

Mr. Hancock

To ask the Secretary of State for Defence how much the series of improved software releases to enhance MBDA's advanced short-range air-to-air missile will cost; when the final improved software releases are expected to be completed; and if he will make a statement. [32156]

Dr. Moonie

The cost of the additional software releases to achieve ASRAAM's Full Operational Capability will be borne by the contractor, MBDA UK Ltd. (formerly Matra BAe Dynamics), and is a matter for them.

The company's aim is to deliver the required missile performance by the end of 2003. If that is not achieved, our agreement with MBDA UK allows for a further software release.