HC Deb 18 December 2002 vol 396 cc805-6W
Mr. Hancock

To ask the Secretary of State for Defence what maintenance work is being done to HMS Ocean; what the cost of this maintenance is; when the decision was made to do the maintenance work; what the original planned cost was of the work; and if he will make a statement. [87803]

Mr. Ingram

HMS Ocean completed a planned upkeep maintenance period in November at a cost of around £5 million. This package of work was completed satisfactorily. During post upkeep trials however, the Port Main Engine suffered a major defect. The defect resulted from a ship system failure which could not have been anticipated and was not related to the work undertaken during the maintenance period. The cost of this repair work is approximately £450,000.