HC Deb 02 December 2002 vol 395 c483W
Mr. Keith Simpson

To ask the Secretary of State for Defence what was the original cost of the refurbishment of his Department's main building; and what the current estimated cost is. [84543]

Dr. Moonie

The costs to the Ministry of Defence will be some £55 million per annum at March 2000 prices over the 30 years of the Public-private Partnership contract. This encompasses the short-term decant arrangements, as well as the long-term provision of a wide variety of services to both the redeveloped main building and the Old War Office building. A fixed price has been negotiated for this PFI project, and only agreed changes to the requirement or deductions for non- performance will have any impact on the cost. To date, the cost has remained unchanged.