§ Mr. BercowTo ask the Solicitor-General if she will list the(a) private finance initiative and (b) public private partnership projects which have been delayed. [44890]
§ The Solicitor-General[holding answer 25 March 2002]: My own Department, the Legal Secretariat to the Law Officers, the Treasury Solicitor's Department and the Serious Fraud Office have not entered into any public-private partnerships or private finance initiatives.
No private finance initiatives or public-private partnership projects entered into by the Crown Prosecution Service have been delayed. The CPS's private finance initiative IT project, 'Compass', has been managed well and is on track. A new PFI contract was agreed with Logica plc in December 2001.
§ Mr. BercowTo ask the Solicitor-General what the difference was between the price offered in reaching referred bidder stage and the final contract price for the five largest PFI contracts let by her Department in each of the last four years; and if she will make a statement. [45680]
§ The Solicitor-General[holding answer 25 March 2002]: My own Department, the Legal Secretariat to the Law Officers, the Treasury Solicitor's Department and the Serious Fraud Office have not entered into any public-private partnerships in each of the last four years.
The Compass project, which is a private finance initiative, is the only relevant contract let by the Crown Prosecution Service in the last four years. The price for the Compass project at preferred bidder stage and the final contract price were identical. There is an allowance of 1 per cent. built into the contract price to take into account any findings arising from a further period of due diligence. The actual contract price is subject to commercial confidentiality.