§ Matthew TaylorTo ask the Secretary of State for Transport, Local Government and the Regions, pursuant to his answer of 16 July 2001,Official Report, column 19W, on PFI, what the average saving is under PFI contracts awarded; and in which projects his Department has identified mistakes in the calculation of the public sector comparator after a PFI contract has been signed. [8141]
§ Mr. JamiesonPPP/PFI deals go ahead only where they demonstrate clear value for money against a public sector comparator. The last survey, which was carried out by Arthur Andersen and the LSE, identified 17 per cent. savings by PPPs against a conventional public sector procurement. However, specific information about savings in PFI contracts can be obtained only at disproportionate cost.